/ 29 Jun 2017

Bohem transforming

Bohem is continuing to make great progress.

The concrete structure is now up to level 20, with the Lift Core completed and the first ‘jumpform’ removed. The gradual transformation is taking place up to various levels :

  • Level 15 : Electrical building services are at the ‘first fix’ stage and internal wall framing has been installed
  • Level 14 : Windows and wall sheeting internally to apartments are in place
  • Level 13 : Apartment ceilings are installed
  • Level 11 : Apartment joinery/ built in cabinetry ready plus floor tiling to apartment bathrooms and balconies

 